PROJECTS — RECORD 02 · OFFICE FIT-OUT

Fintech workspace, Business Bay.

NOVA ANTHILLS INTERIORS LLCHANDED OVER Q3 2025SHEET 05 — PROJECT RECORD

CLIENT

Fintech — name withheld

LOCATION

Business Bay, Dubai

SCOPE

Design + build

SIZE

8,600 SQFT

PROGRAMME

11 weeks

APPROVALS

DM · DCD · NOC

THE BRIEF

A trading and engineering floor, ready before the lease's fit-out period ran out.

The client signed an 8,600 sqft Category A shell with a twelve-week fit-out window written into the lease. They needed glazed meeting suites, acoustic-treated focus rooms, a client-facing front of house, and a full MEP re-route for a dense trading floor — with zero appetite for chasing permits themselves.

WHAT WE DELIVERED

01

Test fits and a locked design in nine working days, priced line by line in the BOQ.

02

Glazed meeting suites and acoustic focus rooms rated for confidential calls.

03

Full MEP re-route: power and data density for a trading floor, new HVAC zoning, lighting design.

04

Client-facing front of house with reception joinery and branded finishes.

05

All permits, inspections and the completion certificate — filed and closed out by us.

Glazed meeting suite with timber table
FIG. 01 — MEETING SUITE, LEVEL 14
Acoustic-treated focus room with soft seating
FIG. 02 — FOCUS ROOMS, ACOUSTIC PARTITIONS
Open workspace with dense workstation layout
FIG. 03 — TRADING FLOOR, WORKSTATION LAYOUT

APPROVALS ON THIS PROJECT

Filed on day three. The client never met a regulator.

Every permit below was prepared, submitted, tracked and closed out by Nova AntHills. The full approvals file was handed over with the keys.

How approvals work
PERMIT RECORD — THIS PROJECTDXB

Decor / fit-out permit

DUBAI MUNICIPALITY

OBTAINED

Fire & life safety approval

DUBAI CIVIL DEFENCE

OBTAINED

Building-management NOC

BUILDING OWNER / FM

OBTAINED

Completion certificate

DUBAI MUNICIPALITY

CLOSED OUT

FULL APPROVALS FILE HANDED OVER AT COMPLETION.

OUTCOME

Handed over in week eleven — one week inside the lease's fit-out window — with a snag list cleared in six working days and the completion certificate closed out before the team moved in.

CLIENT NAME WITHHELD — REFERENCE AVAILABLE AT CONSULTATION.